UC-04 | Production Replanning

Quality hold on Batch F-8011 (Coke Zero · Athy) disrupts adjacent batch F-8009 and cascades to Bottler B delivery. Two human decisions resolve quality risk and bottler service.

Agents
QAPRDORCMPCAS
Human decisions
2
Est. time
6 min
Value at risk
€60K
Stage 1 of 7

Quality hold placed on F-8011

Quality Agent fires hold notification. Production Agent immediately calculates adjacency impact.

QA
Quality AgentProduction AgentTRIGGER09:02:14
Hold placed on Batch F-8011 (Coke Zero · Athy · 2,400 kg). Tank A occupied. Awaiting micro panel — expected hold duration 4 days (ML 78% confidence).
PRD
Production AgentOrchestratorANALYSIS09:02:22
Adjacency check: F-8009 (Fanta Orange) needs Tank A in 2 days. With Tank A blocked and Tank B free in only 6h, F-8009 is at risk of 18 aging days lost.